|
ENERGY REGULATORY COMMISSION’S (ERC)
CASE FILING PROCEDURE
(Download
MS Word version)
A. Applications for
a General Change in Rate Schedules or Revision of Rates
Section 1. Applications for a
General Change in Rate Schedules or Revision of Rates. - Applications for a general change in rate
schedules shall indicate the revised rates applied for and the reasons cited to
justify such revision or adjustment. Rate applications of distribution
utilities that are not yet under performance-based regulation shall conform to
the appropriate form in the attached ERC Standard Forms.
Section 2. Supporting
Documents and Information.
- The application for a general change in rate schedules shall be accompanied
by the following documents and information:
(a)
Schedule A (in ERC Format)
Table
1: Development of Rate Base
Specific Requirements: For Electric
Cooperatives (EC) and Private Utilities (PU)
1.1. Appraisal Report
1.1.1. Independent appraiser should be accredited by ERC
1.1.2. Appraisal Report must be in accordance with the Guidelines for the
Appraisal of Property, Plant and Equipment for Rate Fixing Purposes of ERC
1.1.3 Two (2) copies of Valuation Report of Independent Appraisal Company
1.2. Detailed Breakdown of assets, additions and retirements
after the last approved application up to the present appraisal
1.3. Schedule showing the percentage of local and
foreign cost component of assets under appraisal
1.4. Schedule of rate of depreciation and method used per asset category
1.5. Schedule of utility plant in service for the test year (both depreciable
and non-depreciable assets)
1.5.1. Schedule: Comparison of Utility Plant in Service (Test Year vs. Previous
Year) Assets with more than 100% increase from previous years need detailed
breakdown with corresponding justification
1.6. Schedule of depreciation expense on Appraisal Increase (from last approved
appraisal)
1.6.1. Schedule of depreciation rate
1.7. Schedule of Construction Work-In-Progress (Status and Percentage of
Completion)
1.8. Determination of Cash Working Capital (computation, billing cycle,
supporting documents)
1.9. Schedule of Assets previously disallowed by ERB/ERC indicating
order/decision date, if any
Table
2: Capital Costs
Specific Requirements: For PUs only
2.1. Copy of the Approved Capital Expenditure (CAPEX)
Project/s or the application in the absence of approved CAPEX Project/s for the
Test Year
2.2. Projected Statement of Invested Capital and Rate
of Return for a Five (5) Year Period
2.3. Schedule of Invested Capital and Rate of Return (for the Test Year
period)
2.4. Schedule of Annual Debt Cost Calculation for the Test Year
Specific Requirements: For ECs only
2.1. National Electrification Administration (NEA) Loan
Profile for the Test Year
2.2. Loan Profiles from sources other than NEA for the Test Year
(Include loan profiles for the succeeding year(s) if new loans were acquired
after the test year)
2.3. Detailed Breakdown of the amount of Debt Service reflected in the current
rate application (Uniform Filing Requirements / UFR)
2.4. Written explanation reconciling the differences in total amount of Debt
Service (UFR) (excluding Interest Cost on Cash Working Capital) vs. the Test
Year’s Loan Profile/s (NEA and other sources)
2.5. Copy of the Approved Capital Expenditure (CAPEX) Project/s or the
application in the absence of approved CAPEX Project/s for the Test Year
Table
3: Operation & Maintenance Expense
Specific Requirements: For ECs and PUs
3.1. Power Cost
3.1.1. Generation Cost Schedule for the Test Year
3.1.2. Transmission Cost Schedule for the Test Year
3.1.3. System Loss Schedule for the Test Year
3.1.4. Written explanation reconciling the differences in the amount
reflected in the Generation & Transmission & System Loss Schedules vs.
rate application (UFR)
3.1.5. Sources of Power
i. NPC (Main or Small Power Utilities Group / SPUG),
pls. specify)
ii. Independent Power Producers (IPP)
iii. Self-generation
iv. Others (ex. Other
Distribution Utilities / DUs)
3.1.6. Certified True Copies of Power Bills used in the Test Year
3.2. Explanation on any discrepancy of the amount reflected in the rate application
vs. Audited Financial Statement (F/S)
3.3. Detailed Breakdown of all Expenses/Accounts - with explanation as to the
purpose of expenses (both in hard and electronic copies)
3.4. NEA Cash Approved Budgets for the Test Year (For ECs)
3.5. Top Twenty (20) Uncollectible Accounts (Acct. Code No. 420-904)
3.6. Copies of publications/fliers made for Informational and Instructional
Advertising Expenses for the year 2003 and corresponding costs thereon. (Acct.
No. 420-905-00)
Table
4: Payroll Portion of O & M
Specific Requirements: For ECs and PUs
4.1. Plantilla/Payroll (per employee, latest monthly) basic salary, SSS,
Pag-ibig, PhilHealth, 13th
month pay & other benefits for the Test Year (Use Table 1)
4.2. For the 2 years prior the Test Year, Test Year and the Year after:
4.2.1. Total number of plantilla (permanent)
positions
4.2.3. Number of positions filled-up
4.2.4. Number of vacant positions
4.2.5. Number of contractual employees
4.2.6. Number of casual employees
4.3. Written explanation reconciling the difference in the Plantilla/Payroll vs. the Payroll Cost reflected in the
rate application (if any)
4.4. Certified photocopies of the following issuances: 2003 to present
Specific Requirements: For ECs only
4.5. Wage orders issued affecting the EC’s salaries & wages
4.6. Copy of NEA approval on each of the incentives/ benefits granted by the
cooperative to its officers and employees (Refer to Table 2)
4.7. If applicable, copies of the EC Board Resolution on the
incentives/benefits granted to officers and employees
4.8. If applicable, copies of the Collective Bargaining Agreement (CBA) on
increase in salaries or grant of incentives or benefits
4.9. Details of Pension & Benefits (Acct. No. 430-926-00)
4.10. Officers’ Allowances & Benefits (Acct. No. 433-934-00)
Table
5: Depreciation and Amortization Expense
Table
6: Income Tax & Other Items
(b) Work Papers on Details &
Explanations
1. Audited F/S (Audited F/S of test year)
2. Balance Sheet
3. Income Statement
4. Cash Flow
5. Notes to the Financial Statement
6. Trial Balance
7. Work Papers
7.1. To explain functionalization
of each account and its basis
7.2. To explain calculation of electricity-related amounts/ adjustments
transferred to column 4 of Schedule A
7.3. To allocate electricity-related amounts in column 5 of Schedule A among
the five functions in cols. 6-10
8. Projected Financial Statements for Five (5) Year Period
9. Projected Cash Flow Statements for Five (5) Year Period
(c)
Schedule A-1: Summary of Revenue
1. Sources for all Distribution/Transmission
2. Related Business
(d)
Schedule B in ERC Format: Summary of Cost of Service (CoS)
using Revalued Assets/ Projected Values (For PUs only)
(e)
Schedule C: Cost of Capital
Specific Requirements: For ECs only
1. Calculation/Methodology/Debt Service Details
2. Detailed summary of all components of total EC debt service
3. All supporting documentation including any reports submitted to NEA or Power
Sector Assets and Liabilities Management Corporation (PSALM)
(f)
Schedule D: Functionalization Factors
1. Detailed computation/explanation of any deviation/modification made on
default factors of the UFR Model
2. Method used in the Demand-Customer Split Minimum Plant Method
2.1. Summary of Meters (latest data)
2.1.1. Type, Quantity and Amount
2.1.2. Number and Cost (disposed and under repair)
2.2. Summary of Transformers (latest data)
2.2.1. Type, Quantity and Amount
2.2.2. Number and Cost (disposed and under repair)
2.3. Summary of Poles (latest data)
2.3.1 Type, Quantity and Amount
2.3.2. Number and Cost (disposed)
3. Narrative description of the functionalization
factor if code designation is used
4. The relative (decimal representations of percentages) amounts constituting
the functionalization factors
5. The absolute amounts constituting the factors, i.e. the data used as
numerators and divisors in calculating the functionalization
factors
(g)
Schedule E: Billing Determinants & Customer Class Allocation
1. Sub-Schedule E-1: System Data
Specific Requirements For ECs and PUs
1.1. Basis of kWh Sales
1.1.1. Actual
1.1.2. Average
1.1.3. Annualized
i. Increase or decrease in kWh sales due to
adjustment for changes in customer composition and/or for
changes in the number of customers
ii. Increase or decrease in kWh sales due to adjustment
other than for the effects of customers(e.g.
reclassification of customers), reflecting each adjustment separately
1.2. Basis of kW Demand
1.2.1. Annual Billing Demand (kW) for the test year for customer
classes with demand meters meaning, all customers of
that particular class should have demand meters
1.3. Basis of Number of Customer
1.3.1. Average number of customers
1.3.2. Year-end number of customers
1.4 System Load Factor
1.5. Schedule of Power Interruptions for Five (5) Year
Period
1.6. Narrative explanation for all adjustments made for the Year of the
above schedule
1.7. Frequency Distribution of Customers and kWh consumption of Residential
Customers (Test Year and Current Year)
2. Sub-Schedule E-2: Customer
Adjustments
Specific Requirements: For ECs and PUs
2.1. Does the DU have the following customer classes:
2.1.1. Sale for Resale? If yes:
- Identify the customer/s
- Provide copy of the contract
- When did the sale started?
- What is the rate/kWh charged to his customer?
- To date, does the DU still have this type of customer?
2.1.2. “Others”? If yes:
- Identify the customer/s and give brief description of customer class (e.g.
- Temporary Lightings during fiestas)
- What is the rate/kWh charged to this customer?
- To date, does the DU still have this type of customer?
2.1.3. Large Load? If yes:
- Identify the customer/s
- Provide copy of the contract
- When did the sale start?
- What is the rate/kWh charged to his customer?
- To date, does the DU still have this type of customer?
- From what voltage level does this customer take power?
- What is the product line of this customer?
- Is it considered in the computation of the Total Revenue
Requirement? If not, submit schedule showing the cost of
servicing and revenue derived from the same.
- Provide same schedule for other customers under the same
scenario
2.1.4. Streetlights?
- How does the DU bill this type of customers
(Per number of bulbs/per street/per barangay/per
municipality?)
- Are they metered?
2.1.5. List of Barangay Power Association (BAPA) (For
ECs only)
- Indicate number of mother meters and individual house connections per BAPA
and corresponding kWh Sales
- Identify the customer/s and give brief description of customer class (e.g.
Temporary Lightings during fiestas)
- What is the rate/kWh charged to the customer?
- How does the DU bill this type of customers (Per number of bulbs/per
street/per barangay/per municipality?)
3. Sub-Schedule E-3: Rate of Return
Specific Requirements: For PUs only
3.1. Determination of Return on Rate Base/Weighted Average Cost of Capital
(WACC) (study and supporting documents)
4. Sub-Schedule E-4: Class CoS Analysis
5. Sub-Schedule E-5: Class Allocation
Factors for
5.1. Generation
5.2. Transmission
5.3. Distribution
5.4. Supply
5.5. Metering
(h)
Schedule F: Rate Design
1. Sub-Schedule F-1: Revenue Summary
2. Sub-Schedule F-3: Rate Class Definition
3. Sub-Schedule F-4: Load Research Data
Specific Requirements: For ECs and Pus
3.1. Sub-Schedule F-4.1: Basis of System Peak Demand
3.2. Sub-Schedule F-4.1.1: Total system peak demand and peak demand by rate and
by class for the Test Year and for each month of the Test Year
3.3. Sub-Schedule F-4.1.2: Detailed computation of Coincident and Non-
Coincident Peak per customer class for the Test Year
4. Sub-Schedule F-5: Justification for Consumption Level-Based Rates
5. Sub-Schedule F-6: Proof of Revenue Statement
5.1. Sub-Schedule F-6.1: Comparison of Revenue and Rate (Existing vs. Proposed)
6. Sub-Schedule F-7: Rate Design Analysis Data
6.1. Sub-Schedule F-7.1: Customer Profile and Rate Impact Simulation per
customer class
(i) Schedule H
1. Sub-Schedule H-1: Computation of Inter-Class Cross Subsidy
2. Sub-Schedule H-2: Proof of Revenue Statement
3. Sub-Schedule H-3: Computation of Lifeline Rate
Specific Requirements: For ECs and PUs
3.1. Sub-Schedule H.3.1: Detailed Breakdown of Lifeline Discount granted and
collection of subsidy
3.2. Sub-Schedule H.3.2: Frequency Distribution of Customers and kWh
consumption of Residential Customers (Test Year and Current Year)
(j)
Schedule J: System Losses & Associated Costs
Specific Requirements: For ECs and PUs
1. Proposed cap on the recoverable rate of system losses based on load density,
sales mix, cost of service, delivery voltage, and any other relevant technical
parameters. The supporting data and analysis shall distinguish between
technical and non-technical system losses and differentiate losses based on
customer class.
2. Detailed system loss information for the past five (5) years and any
applicable engineering studies
3. Calculations of all costs directly attributed to system losses
4. Calculations of the rate components for the recovery of costs associated
with system losses in a fashion separate and distinct from other rates; and
5. Plan to reduce system losses over the next five (5) years which shall
include costs and/or investments to attain such deduction
(k)
Schedule K: Rate Schedules for Each Customer
(l)
Schedule L: Non-Recurring Rates & Supporting Cost Data
B. Applications for
Approval of Power Supply Contract
Section 1. Applications for Approval of Power Supply Contract. – Applications for approval of power supply
contract between a distribution utility and power producer, other than those
covered by the Guidelines for the Setting and Approval of Electricity
Generation Rates and Subsidies for Missionary Electrification Areas (ERC
Resolution No. 11, series of 2005, dated 6 July 2005), shall include a
statement of the salient provisions of the said contract, including the
stipulations on the pricing, and a statement of its impact on the overall rates
of the applicant-utility once said contract is approved.
Section 2. Supporting
Documents and Information.
- The application for approval of power supply contract shall be accompanied by
the following documents and information:
(a) Articles of Incorporation of
Generation Company
(b) Securities and Exchange Commission (SEC) Certificate of Registration of the
said Articles of Incorporation of Generation Company
(c) Latest General Information Sheet of Generation Company
(d) Board of Investment (BOI) Certificate of Registration of Generation Company
(e) Environmental Compliance Certificate (ECC) issued by the Department of
Environment and Natural Resources (DENR) to the Generation Company
(f) Power Supply Agreement/Energy Conversion Agreement Contract (PSA/ECA)
(g) Details of the PSA/ECA
1. Executive Summary
2. Sources of Funds/Financial Plans
2.1. Debt/Equity Ratio
2.2. Project Cost
2.3. Annual Interest
2.4. Computation of Return on Investment/WACC
2.5. Certification from the Bank/Lending Institution
specifying the principal amortization, term and interest during the cooperation
period of the loan agreement
3. Purchased Power Rate
3.1. Breakdown of the base prices of Operation and Maintenance, Capacity
Fee, Fixed Operation Fee, and Energy Fee (provide computations)
3.2. Sample Computation of Power Rates with the supporting documents on the
assumptions taken
3.3. If applicable, basis/rationale of indexation and level
of indexation
4. Cash Flow specifying the following:
4.1. Initial Costs
4.2. Breakdown of Operating and Maintenance Expenses
and
4.3. Minimum Energy Off-take (MEOT)
(i) All details on the procurement process of fuel
including requests, proposals received, tender offers, etc.
(j) Copy of Related Agreements (i.e. Transmission Wheeling Contract, Fuel
Supply Agreements, etc.)
(k) Certificate of Compliance (COC) issued by the ERC pursuant to the
Guidelines for the issuance of COC for Generation Companies/Facilities
(l) Certification by NPC on whether or not Transition Supply Contract (TSC)
capacity and energy are expected to be available during the contractual period
(include relevant supporting documentation, data and analysis supporting each
statement)
(m) All relevant technical and economic characteristics of the generation
capacity, installed capacity, mode of operation, and dependable capacity of the
plant
(n) Details on the procurement process used by the Distribution Utility leading
to the selection of the Generation Company including request(s) for proposals,
proposal received by the Distribution Utility, tender offers, etc.
(o) Details regarding transmission projects or grid connection projects
necessary to complement the proposed generation capacity, including the parties
that will develop and/or own such facilities, any costs related to such
project, and specification of the parties responsible for recovery of any costs
related to such projects
(p) Certification regarding the consistencies and inconsistencies between the
proposed generation capacity and the Department of Energy’s (DOE) Philippine
Development Plan (PDP). Any inconsistency shall be supported by relevant
analysis including but not limited to, forecasts and assessment of available
generation capacity and technology mix.
(q) Details regarding the load forecast projections in accordance with the
latest Distribution Development Plan of the Distribution Utility and the
variability of those projections over the proposed contractual period,
including the estimation of the potential for a reduction in load supplied by
the Distribution Utility due to retail competition. Any inconsistency shall be
supported by relevant analysis.
(r) If the application is filed later than two years following the effectivity of the Guidelines for the Recovery of Costs for
the Generation Component of the Distribution Utilities’ Rates, the application
must include an alternative Demand Side Management (DSM) program that could be
implemented by the Distribution Utilities if approved by the ERC. The
Distribution Utility shall submit the projected costs and benefits of the DSM
program.
Section 3. Applications for
Approval of Power Supply Contract between an Electric Cooperative and a New
Power Provider. - The applicant in
applications for approval of power supply agreement between an electric
cooperative and a new power provider (NPP), as the same is defined in the
Guidelines for the Setting and Approval of Electricity Generation Rates and
Subsidies for Missionary Electrification Areas (ERC Resolution No. 11, series
of 2005, dated 6 July 2005), shall comply with the requirements in said
guidelines pertaining to the notification by the electric cooperative of the
launch of the competitive selection process and the requirements pertaining to
the filing and approval of the power supply agreement (PSA) between an electric
cooperative and an NPP and approval of the true cost of generation rate (TCGR).
In these applications, the Commission
will render a decision within ninety (90) days from the date of the filing of
the application, unless it extends the 90-day decision period for a maximum of
ninety (90) days on account of extraordinary circumstances attending the
application. If no decision is rendered within the original or the extended
decision period, the PSA and the NPP TCGR will be deemed approved.
C. Application for
Approval of Electric Distribution Capital Projects
Section 1. In General. - Any plan for expansion or improvement of
distribution facilities shall be reviewed and approved by the Commission to
ensure that all capital projects are optimized and that the contracting and
procurement of the equipment, assets and services have been subjected to
transparent and competitive bidding and purchasing processes to protect public
interest. Applications of this nature shall be governed by the Guidelines to
Govern the Submission, Evaluation and Approval of Electric Distribution Capital
Projects.
Section 2. Application for
Approval of Major Electric Capital Projects. - The application for the approval of any Major
Electric Capital Project/s, as the same is defined in the Guidelines to Govern
the Submission, Evaluation and Approval of Electric Distribution Capital
Projects shall comply with the formal requirements in Rule 3 and shall be
accompanied by the following supporting documents:
(a) Description of the Project
(b) Justifications for the Project (include the adverse effects of the
non-implementation of the proposed Project(s) and impact or benefits of the
proposed Project(s) on the system)
(c) Options/Alternatives considered in lieu of the proposed Project(s)
(d) Five-year Historical and Forecast Planning Data consistent with the
Distribution Development Plant (DDP)
(e) Technical Analysis (Simulation and/or Computation)
(f) Projected Financial & Economic Cost Analysis
1. Impact/effect on rate base of the proposed Project(s)
2. Net Present Value, Internal Rate of Return and Benefit/Cost Ratio analysis
(include analysis of the alternatives)
(g) Conceptual Engineering Design and Drawings
(h) Project Cost Estimates which have to be in reference to a specified design
and bill of materials in the latest Manual of Construction Standards submitted
to the ERC
(i) Project Financing Plan
(j) Proposed Gantt Chart Schedule (include Bidding and Procurement Schedule)
(k) Board Resolution or Secretary’s Certificate approving the proposed
Project(s)
(l) Sworn Statement from the authorized representative of the Electric Utility
that an application for approval from the concerned agencies that may have
interest in the proposed project has been filed /or shall be filed by (specify
date of filing and furnish ERC a copy within 5 days upon filing)
(m) Sworn Statement from the authorized representative of the Electric Utility
that the proposed major capital project is consistent with the DDP. Projects
which are not included in the DDP need justification.
Section 3. Application for
Approval of Major Non-Electric Capital Projects. - The application for the approval of any Major
Non-Electric Capital Project, as the same is defined in the Guidelines to
Govern the Submission, Evaluation and Approval of Electric Distribution Capital
Projects shall comply with the formal requirements in Rule 3 and shall be
accompanied by the following supporting documents:
(a) Description of the Project
(b) Justification for the Project
(c) As-built Design and Drawings, if applicable
(d) Actual Project Cost
(e) Projected Financing Plan
(f) Gantt Chart Schedule
(g) Board Resolution or Secretary’s Certificate approving the proposed
project/s
(h) Sworn Statement from the authorized representative of the Electric Utility
that an application for approval from the concerned agencies that may have
interest in the proposed project has been filed or shall be filed, if
applicable
Section 4. Issuance of
Provisional Authority.
- Upon filing of the application, the Commission may, on its own or upon
motion, grant the issuance of a Provisional Authority (PA) based on the
allegations of the application and on such other documents attached thereto or
submitted by the parties. The Commission, if necessary, may schedule a hearing
for the issuance of a PA not later than thirty (30) days from the filing of the
application. Thereafter, the Commission shall issue a ruling either granting or
denying the PA stating clearly the reasons therefor,
within seventy five (75) days from the filing of the application.
Section 5. Decision.
- Any application for the approval of Major Capital
Projects and/or Major Emergency Capital Projects shall be decided by the
Commission within ninety (90) days from the time the applicant formally offers
its evidence; otherwise, the application shall be deemed approved upon the
lapse of said period.
Section 6. Permit Fee. - For the authorization and approval of Major
Capital Projects and/or Major Emergency Capital Projects, an electric utility
shall be required to pay a permit fee based on the existing schedule of ERC
Fees and Charges.
Section 7. Referral to the
Distribution Management Committee or Technical Consultant. - The Commission may refer to the Distribution
Management Committee or engage the services of a consultant at a reasonable
cost, in the evaluation of any Major Capital Project application submitted to
it for approval. The applicant shall be charged an amount equivalent to the
expenses incurred by the Commission in engaging the services of the consultant,
and said expenses shall be recovered by the applicant as part of the capital
expenditure of the project being evaluated.
Section 8. Reportorial
Requirements. - In addition to the foregoing, the
electric utility shall comply with the reportorial and other requirements
contained in the Guidelines to Govern the Submission, Evaluation and Approval
of Electric Distribution Capital Projects.
D. Applications for
Authorizations as Required by Section 20 (e) and (g) of the Public Service Act
Section 1. In General.
- A distribution utility shall secure
the Commission’s authorization for issuance of stock certificates representing
an increase of capital; for issuance of any share of stock without par value;
or issuance of any bond or other evidence of indebtedness payable in more than
one year from the issuance thereof. It shall also secure the Commission’s
approval to the sale, alienation, mortgage, encumbrance, or lease of its
property, franchises, certificates, privileges, or rights or any part thereof;
merger or consolidation of its property, franchises, certificates, privileges,
or rights or any part thereof, with those of another utility.
Section 2. Supporting
Documents.
- Applications under Section 1 shall
be accompanied by the following documents and information insofar as they are
applicable:
(a) Latest Audited balance Sheet and
Profit and Loss Statement;
(b) Letter of approval of lending institution from where the loan is to be
secured;
(c) List of projects and/or items of equipment and their estimated cost to
which the proceeds of the loan will be utilized;
(d) List of properties to be mortgaged (with specifications);
(e) Details or specifications of the equipment/projects to be purchased; and
(f) Basis/Reasonableness of the estimated cost per project/equipment.
Section 3. Applications for Issuance of any
Bond or Other Evidence of Indebtedness Payable in More Than One Year To Fund Electric Capital Projects. - If the issuance of bonds or other evidence of
indebtedness payable in more than one year from issuance is for the purpose of
funding the distribution utility’s electric capital projects, the application
for authorization therefor and for the mortgage or
encumbrance of property to secure such indebtedness, if such is the case, shall
be joined with the application for approval of said electric capital projects
to be filed under Rule 20 (C).
Section 4. Issuance of
Provisional Authority.
- Upon filing of the application under Section 1, the Commission may, on its
own or upon motion, grant the issuance of a Provisional Authority (PA) based on
the allegations of the application and on such other documents attached thereto
or submitted by the parties. The Commission, if necessary, may schedule a
hearing for the issuance of a PA not later than thirty (30) days from the
filing of the application. Thereafter, the Commission shall issue a ruling
either granting or denying the PA stating clearly the reasons therefor, within seventy five (75) days from the filing of
the application.
Section 5. Decision. - Any application under Section 1 shall be decided
by the Commission within ninety (90) days from the time the applicant formally
offers its evidence; otherwise, the application shall be deemed approved upon
the lapse of said period.
E. Consumer
Complaints
Section 1. Intent, Application and Scope. - It is the Commission’s intent that disputes
between regulated companies and their customers are resolved as quickly,
effectively, and inexpensively as possible. This rule establishes informal
customer complaint procedures that are designed to address disputes, subject to
the Commission’s jurisdiction, that occur between distribution utilities and
individual customers. It provides for expedited processes for customer
complaints that can be resolved quickly by the customer and the distribution
utility. It also provides a process for informal Commission staff resolution of
complaints that cannot be resolved by the distribution utility and the
customer.
Section 2. Informal Process
for Consumer Complaints.
-
(a) Any customer of a distribution
utility may file a complaint with the Commission’s Consumer Affairs Service or
with its Visayas or Mindanao Field Offices whenever the customer has an unresolved
dispute with the distribution utility regarding the electric service that is
subject to the Commission’s regulation. The complaint shall be communicated in
writing. The complaint shall include the name of the distribution utility
against which the complaint is made, the name of the customer and the
customer’s service address, and a description of the complaint.
(b) The Commission staff handling the
complaint will determine if the customer has earlier contacted the distribution
utility and referred the complaint to the distribution utility’s Consumer
Welfare Desk (CWD) officer for resolution. If the customer has not yet
contacted the distribution utility, the Commission staff will advise the
customer to refer the complaint first to the distribution utility’s CWD
officer.
(c) If the complaint has already been
referred to the distribution utility’s CWD officer and no resolution has been
reached, the Commission staff shall notify the distribution utility of the
complaint and request a written response from the distribution utility within
five (5) days from receipt of the notice, copy furnished the customer. The
notification to the distribution utility by the Commission staff will be
addressed to the distribution utility’s CWD officer or any other responsible
officer.
(d) The distribution utility’s response to the Commission staff shall explain
the likely cause of the problem, all actions taken by the distribution utility
to resolve the customer’s complaint at the CWD level, and the distribution
utility’s proposed resolution of the complaint and shall answer every specific
question raised by the Commission staff in the notification. The distribution
utility’s response shall also include communications sent to the customer that
contain the distribution utility’s proposed resolution of the complaint or
statement of position in addressing or resolving the complaint.
(e) If a customer objects to the
distribution utility’s response to the complaint or rejects the distribution
utility’s proposed resolution thereof, the customer may request further review
of the complaint by Commission staff. Commission staff will then propose a
resolution of the complaint. Before coming up with a proposed resolution of the
complaint, the Commission staff may conduct informal conference between the
parties and direct the submission of copies of bills, billing statements, field
reports, photographs, documents, or other information in the participants’
possession that may be necessary.
(f) If the proposed resolution is
acceptable, the customer and the distribution utility shall manifest their
acquiescence thereto in writing. If the customer or the distribution utility is
not in agreement with Commission staff’s proposed resolution and no other
resolution is agreed upon by the parties, the complaint shall be endorsed for
hearing and dispute resolution by the Commission.
Section 3. Formal Hearing. -
(a) After the Commission staff endorses the complaint for hearing, the customer shall
be required to verify his or her complaint, if the same has not yet been
verified, and the complaint shall be docketed as a consumer complaint and
assigned a case number. Thereafter, the Commission shall issue an order
requiring the respondent to file its answer thereto within fifteen (15) days
from receipt of the order. If the respondent fails to file its answer within
the period, the Commission shall render a decision based on the records.
(b) After respondent files its answer, the Commission shall determine if the
case can be tried under the summary procedure in Section 2 of Rule 17. If the
Commission determines that this procedure is applicable, it shall issue an
order to this effect as stated in Section 2 of Rule 17. If the Commission
determines otherwise, it shall set the case for pre-trial conference and
require the parties to submit their pre-trial briefs in accordance with Section
3 of Rule 16.
F.
Commission-initiated Investigation
Section 1. Inquiry of the
Commission. - The Commission may motu proprio initiate an action
or inquiry against any person or entity when so required by law, national or
public interest, and/or in its exercise of any of the powers and functions
vested upon it by Republic Act No. 9136 or any other law enforced and
administered by it.
Section 2. Contents of the
Order.
- In the exercise of its prerogative,
the Commission may commence such hearing or inquiry by an order to show cause,
setting forth the grounds and legal bases for such order. The order shall state
the facts constituting the violation and also the range or extent of the
sanction or penalty that may be imposed should the violation be substantiated,
and shall be served upon the person or respondent being investigated.
Section 3. Answer.
- Within a period of fifteen (15) days from receipt
of a show cause order, the respondent shall file an answer in accordance with
Rule 5.
Section 4. Disposition. - If the Commission finds the answer sufficient in
form and substance to warrant termination of the inquiry, it shall issue an
order to that effect; otherwise, it shall proceed to conduct the hearing on the
matter.
Section 5. Offers of
Settlement. - Any party to an administrative
proceeding may, at any time before a decision is rendered, make an offer to the
Commission conditionally or otherwise for a consented decree, voluntary
compliance or desistance and other settlement of the case. The offer and any or
all of the ultimate facts upon which the offer is based shall be considered for
settlement purposes only, and shall not be used as evidence against any party
for any other purpose and shall not constitute an admission by the party making
the offer of any violation of the laws, rules, regulation, orders and
resolution of the Commission, nor as a waiver to file any warranted criminal
action.
Section 6. Cease and Desist Order. - In appropriate cases, the Commission shall issue
Cease and Desist Order after due notice and hearing.
Section 7. Imposition of
Fines and Penalties. - The imposition
of administrative fines and penalties shall be governed by the Guidelines to
Govern the Imposition of Administrative Sanctions in the Form of Fines and
Penalties Pursuant to Section 46 of Republic Act No. 9136, as amended.
G. Compliance
Filings with the Commission
Section 1. In General. - When the Commission issues an order that
authorizes or requires a party to make a filing to implement specific terms of
the order or to comply with conditions for the issuance thereof with respect to
the issues resolved in the proceeding, the filing is deemed a “compliance
filing”. A compliance filing is made under the docket number of the order to
which it relates.
If the Commission in its order
directs a party to initiate an entirely new proceeding, such filing made in
compliance with said directive will be assigned a new docket number, treated as
a separate application or petition, and covered by the same rules applicable to
all other applications or petitions.
Section 2. Reporting
Requirement. - The Commission may, in its order,
require a party to report periodically to the Commission with respect to a
subject matter stated therein. The reports must be filed under the docket
number of the proceeding in which the order is entered, unless otherwise
specified in the order establishing the requirement or directed by the
Commission.
Section 3. Compliance filing
pursuant to certain Rules or Guidelines adopted by the Commission.
- When the Commission adopts certain rules
authorizing or requiring a party to make a filing in accordance therewith, the
filing is likewise deemed a “compliance filing”. This compliance filing is
filed with the Commission’s Docket Section, which will assign it a separate
number, and must include the following:
(a) A verified cover letter that
identifies the specific rules to which the filing relates, the period covered,
if applicable, and the name, address and contact number of the person making
the filing, and summary of the compliance; and
(b) All the pertinent or required documents to be submitted in support of the
compliance filing as provided in the applicable rules or as may be required by
the Commission.
Section 4. Commission Action
on Compliance Filings under Section 3.
- Within fifteen (15) days from the filing, the
Commission shall make a determination of the completeness of the submission. If
it finds that there are still documents and other data that must be submitted,
it shall issue an order directing the submission of such other documents and
data. In such case, the filing shall be deemed to have been made only upon the
receipt by the Commission of such additional documents and data.
After consideration of all the
documents submitted in support of the compliance filing, the Commission may
enter an order approving the compliance filing or rejecting the same or any
portion of the filing that fails to comply. However, if the rules to which the
compliance filing relates provide for the automatic approval thereof upon the
lapse of a specified period stated therein if no decision is reached thereon by
the Commission, then the filing shall be deemed approved upon the lapse of the
period or any extension thereto made by the Commission, as may be the case.
|